Helper Resources When Operations use more than one Resource, you have a Primary Resource and Helper Resources. The scheduling algorithm works so that the Primary Resource is scheduled first, and then it looks for Helper Resources that are available at the same time. The Primary Resource will determine the length of the Operation, so it should be […]

Read More

Resource Mappings

Red = Can be Imported * = Required Name Description Type Values Active (Inherited from BaseResource.) Boolean ActivitiesFinished Indicates the number of Activities that the Resource has Finished since the last Performance Reset.(Inherited from InternalResource.) Analysis If overridden in a parent class, returns a string containing analysis about the object. Else returns an empty string.(Inherited […]