What is Sales Order Pegging?

  • Sales Order Pegging allows the user to see the production jobs that feed into sales orders
  • In the Gantt Pane, clicking on a production order will display arrows that show the path of a production order into subsequent sales orders, and clicking on a sales order will show which production orders it’s pulling material from.

pegging1

  • If a sales order has the materials requirement set to “Constrain by Available Date”, and the production order becomes late, the sales order will be delayed and pushed back on the Gantt. If it’s not set to “Constrain by Available Date”, the sales order will change color to indicate that the materials requirement needed won’t be satisfied, but the job will not move.
  • The details of this delay can be found in the impact monitor

pegging2

  • In the jobs dialogue window you can also see the connected jobs by clicking on the Connected Jobs Gantt tab

pegging3